Grid history

Northern Virginia

Mid-Atlantic US · 485 facilities from 92 named operators. Counts and floor area only; there is no megawatt figure on record for these buildings.

Q3 2026 · 2 submarkets · all facilities

Operational
244
49,329,035 sf
Under construction
82
25,684,893 sf
Planned
159
64,218,830 sf
Cancelled
0
withdrawn or rejected

Largest operators

By buildings held in this market.

  • Amazon61
  • Compass Datacenters22
  • Microsoft18
  • Equinix16
  • CloudHQ13
  • QTS12
  • NTT12
  • Iron Mountain12
  • Vantage Data Centers7
  • WATERSIDE I LLC6

Serving utilities

Matched by retail service territory.

  • NORTHERN VIRGINIA ELEC COOP264
  • VIRGINIA ELECTRIC & POWER CO221

Submarkets

Counties, used as submarkets.

  • Prince William County, VA246
  • Loudoun County, VA239

Closest to a substation

Nearest substation and distance. datacenterHawk has no substation entity at all; this is additive.

FacilityStageSubstationDistanceMax kVNearest ≥115 kV line
EquinixPlannedUNKNOWN11700077 m11577 m
DIGITAL LOUDOUN PKWY CTR NORTH LLCOperationalUNKNOWN146358123 m230123 m
21635 RED RUM DROperationalUNKNOWN146360131 m—1.3 km
AmazonOperationalDAVIS DRIVE134 m230134 m
21955 LOUDOUN COUNTY PKWYOperationalUNKNOWN177029141 m—888 m
GI TC DEVIN SHAFRON LLCOperationalUNKNOWN146358142 m230142 m
44470 CHILUM PLOperationalNIVO142 m—560 m
AmazonOperationalYARDLEY RIDGE144 m230119 m
AmazonOperationalPOLAND RD154 m230154 m
NTTOperationalBEAUMEADE164 m230145 m
INTERGATE ASHBURN I LLCOperationalUNKNOWN146360165 m—1.2 km
10050 BRICKYARD WAYUnder constructionVMEA PEAKING GEN188 m—91 m
QTSOperationalUNKNOWN146361190 m23048 m
Digital RealtyOperationalUNKNOWN117006191 m230160 m
DIGITAL LOUDOUN PKWY CTR NORTH LLCOperationalUNKNOWN146358194 m230194 m
21631 RED RUM DROperationalUNKNOWN146360194 m—1.3 km
AmazonOperationalPOLAND RD195 m230195 m
INTERGATE ASHBURN I LLCOperationalUNKNOWN146360197 m—1.2 km
pwc.buildings:||Digital_Gateway_North|duPlannedUNKNOWN116755200 m115174 m
HAYDEN TECHNOLOGIES LLCOperationalUNKNOWN176933201 m230103 m
Hawk reports this market in megawatts of commissioned, available, under-construction and planned power, plus absorption and a vacancy rate. Every one of those is a function of what is leased, and leases are not on record. Floor area and building counts are the honest substitute.
    Northern Virginia data centre market — ZoningLabs