Wheelabrator Baltimore Refuse
Wheelabrator Baltimore Refuse is a 65 MW biomass power plant in Baltimore City County, Maryland, operated by Wheelabrator Environmental Systems. EIA-860M lists 2 generating units here, inside PJM. Its units entered service between 1984 and 2001.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Nameplate capacity
- 64.5 MW
- 61.3 MW net summer
- Generating units
- 2
- In service
- 1984–2001
- EIA plant ID
- 10629
Where it is
Loading map…
- County
- Baltimore City County, Maryland
- Coordinates
- 39.266, -76.6296
- Balancing authority
- PJM
- Sector
- IPP CHP
Units, technology and status
- Operator of record
- Wheelabrator Environmental Systems
- Primary energy source
- Biomass
- Technologies
- Municipal Solid Waste
- Status
- Operating
Every plant Wheelabrator Environmental Systems reports to EIA →
Wheelabrator Baltimore Refuse: FAQ
- Where is Wheelabrator Baltimore Refuse?
- In Baltimore City County, Maryland (MD). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
- How big is Wheelabrator Baltimore Refuse?
- 65 MW of nameplate capacity across 2 units, as of the EIA-860M release for 2026-07.
- Who owns Wheelabrator Baltimore Refuse?
- EIA-860M names Wheelabrator Environmental Systems as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
- Is this the same as Wheelabrator Baltimore Refuse LLC?
- Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Wheelabrator Environmental Systems here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Wheelabrator Baltimore Refuse LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
- Is Wheelabrator Baltimore Refuse still running?
- EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.