Fries Hydroelectric Project

Fries Hydroelectric Project is a 5 MW hydroelectric power plant in Grayson County, Virginia, operated by Central Rivers Power US, LLC. It has 4 generating units here, inside PJM. Its units entered service between 1933 and 1981.

As of 2026-07 · updated 2026-07-31 · Source: EIA-860M

Nameplate capacity
5.4 MW
5 MW net summer
Generating units
4
In service
1933–1981
Plant code
10798

Where it is

Loading map…
County
Grayson County, Virginia
Coordinates
36.7151, -80.9856
Balancing authority
PJM
Sector
IPP Non-CHP

Units, technology and status

Operator of record
Central Rivers Power US, LLC
Primary energy source
Hydro
Technologies
Conventional Hydroelectric
Status
Operating

Every plant operated by Central Rivers Power US, LLC →

Fries Hydroelectric Project: FAQ

Where is Fries Hydroelectric Project?
In Grayson County, Virginia (VA). The map on this page is placed at the plant's reported coordinates, which locate the site rather than any individual unit.
How big is Fries Hydroelectric Project?
5 MW of nameplate capacity across 4 units, as of 2026-07.
Who owns Fries Hydroelectric Project?
Central Rivers Power US, LLC is the operator of record. That is not always the ultimate owner.
Is this the same as Fries Hydroelectric Project LLC?
Probably, but the plant data does not say. It records a plant name and an operator — Central Rivers Power US, LLC here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Fries Hydroelectric Project LLC" usually means this site. This page does not assert a corporate structure it cannot see.
Is Fries Hydroelectric Project still running?
Its status is "Operating" as of 2026-07. Statuses change monthly, and this page is updated monthly.