Planned battery storage projects in Colorado
What EIA-860M's Planned sheet says is coming in Colorado: 10 battery storage projects totalling 2 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Planned projects
- 10
- 13 generating units
- Proposed capacity
- 2 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2030
Map of planned battery storage projects in Colorado
Loading map…
List of planned battery storage projects in Colorado
| Fortress 12 technologies | Fortress Solar 1 LLC | Morgan | 398.9 | 3 | 2028 | Regulatory approvals pending. Not under construction |
| South Platte StorageBatteries | South Platte Storage, LLC | Morgan | 250 | 1 | 2027 | Under construction |
| Dry Land Prairie Energy StorageBatteries | Dry Land Prairie Energy Storage, LLC | Cheyenne | 250 | 1 | 2026 | Under construction |
| Grand Valley Solar Generation and BESS2 technologies | GRVA bn, LLC | Mesa | 200 | 2 | 2029 | Regulatory approvals pending. Not under construction |
| Morel Energy StorageBatteries | Morel Energy Storage LLC | Moffat | 200 | 1 | 2030 | Regulatory approvals received. Not under construction |
| Spindle BESSBatteries | Spindle Battery LLC | Weld | 199 | 1 | 2026 | Under construction |
| Carousel Energy Storage, LLCBatteries | Carousel Energy Storage, LLC | Kit Carson | 149.6 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Drennan Energy StorageBatteries | Drennan Energy Storage LLC | El Paso | 100 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| Weld Energy StorageBatteries | Weld Energy Storage, LLC | Weld | 100 | 1 | 2026 | Under construction |
| Pueblo Airport Generating StationBatteries | Black Hills Service Company LLC | Pueblo | 50 | 1 | 2027 | Regulatory approvals pending. Not under construction |
Where they are in the build
- Regulatory approvals pending. Not under construction4
- Under construction3
- Regulatory approvals received. Not under construction2
- Under construction1
Planned battery storage projects in Colorado: FAQ
- How many battery storage projects are planned in Colorado?
- 10, for 2 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
- What do the status letters mean?
- EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.