Planned battery storage projects in Hawaii
What is planned in Hawaii as of 2026-07: 6 battery storage projects totalling 278 MW, each with the in-service year its developer reported and its construction status. A planned project is not a built one.
As of 2026-07 · updated 2026-07-31 · Source: EIA-860M
- Planned projects
- 6
- 9 generating units
- Proposed capacity
- 278 MW
- Earliest in-service year
- 2026
- Latest in-service year
- 2030
Map of planned battery storage projects in Hawaii
Loading map…
List of planned battery storage projects in Hawaii
| Keamuku2 technologies | AES Clean Energy | Hawaii | 172 | 2 | 2030 | Regulatory approvals pending. Not under construction |
|---|---|---|---|---|---|---|
| AES Waiawa Phase 2 Solar2 technologies | AES Distributed Energy | Honolulu | 60 | 2 | 2026 | Under construction |
| AES Mountain View Solar2 technologies | AES Distributed Energy | Honolulu | 14 | 2 | 2026 | Under construction |
| KRS I Anahola Solar HybridBatteries | Kauai Island Utility Cooperative | Kauai | 12 | 1 | 2027 | Planned for installation |
| KRS II Koloa SolarBatteries | Kauai Island Utility Cooperative | Kauai | 12 | 1 | 2027 | Planned for installation |
| Hamakua Energy PlantBatteries | Hamakua Energy LP | Hawaii | 7.5 | 1 | 2030 | Planned for installation |
Where they are in the build
- Planned for installation3
- Under construction2
- Regulatory approvals pending. Not under construction1
Planned battery storage projects in Hawaii: FAQ
- How many battery storage projects are planned in Hawaii?
- 6, for 278 MW of nameplate capacity. These are generators developers have reported as planned, not generators that exist.
- What do the status letters mean?
- Each planned generator carries a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. Projects are canceled or postponed, and move in and out of the planned list month to month. This page lists what was planned as of 2026-07 and nothing more.