Planned battery storage projects in North Carolina

What EIA-860M's Planned sheet says is coming in North Carolina: 11 battery storage projects totalling 374 MW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
11
11 generating units
Proposed capacity
374 MW
Earliest in-service year
2026
Latest in-service year
2027

Map of planned battery storage projects in North Carolina

Loading map…

List of planned battery storage projects in North Carolina

Planned battery storage projects in North Carolina
Allen 2 BESSBatteriesDuke Energy Carolinas, LLCGaston16712027Planned for installation
New Hill 1 BatteryBatteriesDuke Energy Progress - (NC)Wake5612027Under construction
Maiden Creek BatteryBatteriesDuke Energy Carolinas, LLCCatawba5012027Under construction
Craggy Energy StorageBatteriesDuke Energy Carolinas, LLCBuncombe30.512026Under construction
Elm City BESSBatteriesDuke Energy Progress - (NC)Wilson2012026Under construction
Asheville BESSBatteriesDuke Energy Progress - (NC)Buncombe17.312026Under construction
Parkwood BESSBatteriesNorth Carolina El Member CorpUnion11.612026Under construction
Warsaw 2 Energy StorageBatteriesDuke Energy Progress - (NC)Duplin1112026Under construction
Tanglewood BESSBatteriesNorth Carolina El Member CorpPasquotank3.912026Under construction
Windsor BESSBatteriesNorth Carolina El Member CorpBertie3.912026Under construction
Nebo Energy StorageBatteriesDuke Energy Carolinas, LLCBurke2.712026Under construction

Where they are in the build

  • Under construction6
  • Under construction4
  • Planned for installation1

Planned battery storage projects in North Carolina: FAQ

How many battery storage projects are planned in North Carolina?
11, for 374 MW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.