Planned battery storage projects in Oregon
What is planned in Oregon as of 2026-07: 7 battery storage projects totalling 5 GW, each with the in-service year its developer reported and its construction status. A planned project is not a built one.
As of 2026-07 · updated 2026-07-31 · Source: EIA-860M
- Planned projects
- 7
- 11 generating units
- Proposed capacity
- 5 GW
- Earliest in-service year
- 2027
- Latest in-service year
- 2029
Map of planned battery storage projects in Oregon
Loading map…
List of planned battery storage projects in Oregon
| Sunstone Solar2 technologies | Sunstone Solar, LLC | Morrow | 2,400 | 2 | 2027 | Regulatory approvals pending. Not under construction |
|---|---|---|---|---|---|---|
| Deschutes Solar and BESS2 technologies | DECH bn, LLC | Wasco | 2,000 | 2 | 2029 | Regulatory approvals pending. Not under construction |
| Salmonfly Solar and Storage2 technologies | BrightNight Power | Jefferson | 494 | 2 | 2029 | Regulatory approvals pending. Not under construction |
| Biglow Solar Generation and BESS2 technologies | BIGL bn, LLC | Sherman | 250 | 2 | 2027 | Regulatory approvals pending. Not under construction |
| Tualatin Battery Energy Storage SystemBatteries | TUAL bn, LLC | Washington | 200 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Shutler Energy StorageBatteries | Avangrid Power LLC | Gilliam | 41 | 1 | 2028 | Under construction |
| OIT BESSBatteries | PacifiCorp | Klamath | 2 | 1 | 2027 | Under construction |
Where they are in the build
- Regulatory approvals pending. Not under construction5
- Under construction2
Planned battery storage projects in Oregon: FAQ
- How many battery storage projects are planned in Oregon?
- 7, for 5 GW of nameplate capacity. These are generators developers have reported as planned, not generators that exist.
- What do the status letters mean?
- Each planned generator carries a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. Projects are canceled or postponed, and move in and out of the planned list month to month. This page lists what was planned as of 2026-07 and nothing more.