Planned hydroelectric power plants in Mississippi

What EIA-860M's Planned sheet says is coming in Mississippi: 4 hydroelectric power plants totalling 35 MW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
4
8 generating units
Proposed capacity
35 MW
Earliest in-service year
2028
Latest in-service year
2028

Map of planned hydroelectric power plants in Mississippi

Loading map…

List of planned hydroelectric power plants in Mississippi

Planned hydroelectric power plants in Mississippi
Sardis Lake Hydroelectric ProjectConventional HydroelectricRye DevelopmentPanola1522028Planned for installation
Grenada Lake Hydroelectric ProjectConventional HydroelectricRye DevelopmentGrenada1022028Planned for installation
Arkabutla Lake Hydroelectric ProjectConventional HydroelectricRye DevelopmentDeSoto522028Planned for installation
Enid Lake Hydroelectric ProjectConventional HydroelectricRye DevelopmentPanola522028Planned for installation

Where they are in the build

  • Planned for installation4

Planned hydroelectric power plants in Mississippi: FAQ

How many hydroelectric power plants are planned in Mississippi?
4, for 35 MW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.