Planned natural gas power plants in Utah

What EIA-860M's Planned sheet says is coming in Utah: 2 natural gas power plants totalling 22 MW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
2
9 generating units
Proposed capacity
22 MW
Earliest in-service year
2026
Latest in-service year
2027

Map of planned natural gas power plants in Utah

Loading map…

List of planned natural gas power plants in Utah

Planned natural gas power plants in Utah
PaysonNatural Gas Internal Combustion EnginePayson City CorporationUtah14.462026Construction complete
Brigham City GasNatural Gas Internal Combustion EngineBrigham City CorporationBox Elder7.532027Regulatory approvals received. Not under construction

Where they are in the build

  • Construction complete1
  • Regulatory approvals received. Not under construction1

Planned natural gas power plants in Utah: FAQ

How many natural gas power plants are planned in Utah?
2, for 22 MW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.