Planned solar farms in Louisiana
What is planned in Louisiana as of 2026-07: 10 solar farms totalling 1 GW, each with the in-service year its developer reported and its construction status. A planned project is not a built one.
As of 2026-07 · updated 2026-07-31 · Source: EIA-860M
- Planned projects
- 10
- 10 generating units
- Proposed capacity
- 1 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2028
Map of planned solar farms in Louisiana
Loading map…
List of planned solar farms in Louisiana
| Singer SolarSolar Photovoltaic | Singer Solar, LLC | Beauregard | 300 | 1 | 2027 | Planned for installation |
|---|---|---|---|---|---|---|
| Dolet Hills SolarSolar Photovoltaic | Dolet Hills Solar | DeSoto | 240 | 1 | 2026 | Under construction |
| Hollis Creek SolarSolar Photovoltaic | Hollis Creek PV I, LLC | Sabine | 220 | 1 | 2027 | Under construction |
| Beekman SolarSolar Photovoltaic | Beekman PV I, LLC | Morehouse | 206.8 | 1 | 2027 | Under construction |
| Bogalusa West Solar StationSolar Photovoltaic | Entergy Louisiana LLC | Washington | 200 | 1 | 2028 | Planned for installation |
| Mowata SolarSolar Photovoltaic | Lightsource Renewable Energy Asset Management, LLC | Acadia | 150 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Delta Solar PlantSolar Photovoltaic | Entergy Mississippi LLC | Bolivar | 80 | 1 | 2027 | Planned for installation |
| SR South BastropSolar Photovoltaic | SR South Bastrop, LLC | Morehouse | 4.8 | 1 | 2026 | Under construction |
| SR WinnsboroSolar Photovoltaic | SR Winnsboro, LLC | Franklin | 4.8 | 1 | 2026 | Under construction |
| SR SunsetSolar Photovoltaic | SR Sunset, LLC | St Landry | 4.3 | 1 | 2027 | Regulatory approvals received. Not under construction |
Where they are in the build
- Under construction4
- Planned for installation3
- Under construction1
- Regulatory approvals pending. Not under construction1
- Regulatory approvals received. Not under construction1
Planned solar farms in Louisiana: FAQ
- How many solar farms are planned in Louisiana?
- 10, for 1 GW of nameplate capacity. These are generators developers have reported as planned, not generators that exist.
- What do the status letters mean?
- Each planned generator carries a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. Projects are canceled or postponed, and move in and out of the planned list month to month. This page lists what was planned as of 2026-07 and nothing more.