Planned solar farms in Louisiana
What EIA-860M's Planned sheet says is coming in Louisiana: 10 solar farms totalling 1 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Planned projects
- 10
- 10 generating units
- Proposed capacity
- 1 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2028
Map of planned solar farms in Louisiana
Loading map…
List of planned solar farms in Louisiana
| Singer SolarSolar Photovoltaic | Singer Solar, LLC | Beauregard | 300 | 1 | 2027 | Planned for installation |
| Dolet Hills SolarSolar Photovoltaic | Dolet Hills Solar | DeSoto | 240 | 1 | 2026 | Under construction |
| Hollis Creek SolarSolar Photovoltaic | Hollis Creek PV I, LLC | Sabine | 220 | 1 | 2027 | Under construction |
| Beekman SolarSolar Photovoltaic | Beekman PV I, LLC | Morehouse | 206.8 | 1 | 2027 | Under construction |
| Bogalusa West Solar StationSolar Photovoltaic | Entergy Louisiana LLC | Washington | 200 | 1 | 2028 | Planned for installation |
| Mowata SolarSolar Photovoltaic | Lightsource Renewable Energy Asset Management, LLC | Acadia | 150 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Delta Solar PlantSolar Photovoltaic | Entergy Mississippi LLC | Bolivar | 80 | 1 | 2027 | Planned for installation |
| SR South BastropSolar Photovoltaic | SR South Bastrop, LLC | Morehouse | 4.8 | 1 | 2026 | Under construction |
| SR WinnsboroSolar Photovoltaic | SR Winnsboro, LLC | Franklin | 4.8 | 1 | 2026 | Under construction |
| SR SunsetSolar Photovoltaic | SR Sunset, LLC | St Landry | 4.3 | 1 | 2027 | Regulatory approvals received. Not under construction |
Where they are in the build
- Under construction4
- Planned for installation3
- Under construction1
- Regulatory approvals pending. Not under construction1
- Regulatory approvals received. Not under construction1
Planned solar farms in Louisiana: FAQ
- How many solar farms are planned in Louisiana?
- 10, for 1 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
- What do the status letters mean?
- EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.