Planned wind farms in Indiana

What EIA-860M's Planned sheet says is coming in Indiana: 2 wind farms totalling 400 MW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
2
2 generating units
Proposed capacity
400 MW
Earliest in-service year
2026
Latest in-service year
2027

Map of planned wind farms in Indiana

Loading map…

List of planned wind farms in Indiana

Planned wind farms in Indiana
Templeton WindOnshore Wind TurbineTempleton Wind Energy Center, LLCBenton200.212027Regulatory approvals received. Not under construction
Blackford WindOnshore Wind TurbineLeeward Asset Management, LLCBlackford20012026Under construction

Where they are in the build

  • Regulatory approvals received. Not under construction1
  • Under construction1

Planned wind farms in Indiana: FAQ

How many wind farms are planned in Indiana?
2, for 400 MW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.