Old Frontier Solar III is a 4 MW battery storage project in Franklin County, Massachusetts, operated by Old Frontier Solar III PV, LLC. It has 2 generating units here, inside ISO New England. Its units entered service in 2022.

As of 2026-07 · updated 2026-07-31 · Source: EIA-860M

Nameplate capacity
4 MW
4 MW net summer
Generating units
2
In service
2022
Plant code
68069

Where it is

Loading map…
County
Franklin County, Massachusetts
Coordinates
42.494, -72.6225
Balancing authority
ISNE
Sector
IPP Non-CHP

Units, technology and status

Operator of record
Old Frontier Solar III PV, LLC
Primary energy source
Battery
Technologies
Batteries, Solar Photovoltaic
Status
Operating

This site runs on more than one energy source. Capacity splits: Battery 2 MW, Solar 2 MW. It is listed here under Battery, the energy source with the most capacity.

Old Frontier Solar III: FAQ

Where is Old Frontier Solar III?
In Franklin County, Massachusetts (MA). The map on this page is placed at the plant's reported coordinates, which locate the site rather than any individual unit.
How big is Old Frontier Solar III?
4 MW of nameplate capacity across 2 units, as of 2026-07.
Who owns Old Frontier Solar III?
Old Frontier Solar III PV, LLC is the operator of record. That is not always the ultimate owner.
Is this the same as Old Frontier Solar III LLC?
Probably, but the plant data does not say. It records a plant name and an operator — Old Frontier Solar III PV, LLC here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Old Frontier Solar III LLC" usually means this site. This page does not assert a corporate structure it cannot see.
Is Old Frontier Solar III still running?
Its status is "Operating" as of 2026-07. Statuses change monthly, and this page is updated monthly.