Cross Trails Energy Storage Project is a 58 MW battery storage project in Scurry County, Texas, operated by Energy Vault, Inc.. EIA-860M lists 1 generating unit here, inside ERCOT. Its unit entered service in 2025.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Nameplate capacity
58.3 MW
57 MW net summer
Generating units
1
In service
2025
EIA plant ID
69244

Where it is

Loading map…
County
Scurry County, Texas
Coordinates
32.745, -100.757
Balancing authority
ERCO
Sector
IPP Non-CHP

Units, technology and status

Operator of record
Energy Vault, Inc.
Primary energy source
Battery
Technologies
Batteries
Status
Operating

Every plant Energy Vault, Inc. reports to EIA →

Cross Trails Energy Storage Project: FAQ

Where is Cross Trails Energy Storage Project?
In Scurry County, Texas (TX). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
How big is Cross Trails Energy Storage Project?
58 MW of nameplate capacity across 1 unit, as of the EIA-860M release for 2026-07.
Who owns Cross Trails Energy Storage Project?
EIA-860M names Energy Vault, Inc. as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
Is this the same as Cross Trails Energy Storage Project LLC?
Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Energy Vault, Inc. here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Cross Trails Energy Storage Project LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
Is Cross Trails Energy Storage Project still running?
EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.