Mead Coated Board
Mead Coated Board is a 121 MW biomass power plant in Russell County, Alabama, operated by Mead Coated Board Inc. EIA-860M lists 3 generating units here. Its units entered service between 1966 and 1998.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Nameplate capacity
- 120.5 MW
- 116.5 MW net summer
- Generating units
- 3
- In service
- 1966–1998
- EIA plant ID
- 54802
Where it is
Loading map…
- County
- Russell County, Alabama
- Coordinates
- 32.1761, -85.0272
- Balancing authority
- SOCO
- Sector
- Industrial CHP
Units, technology and status
- Operator of record
- Mead Coated Board Inc
- Primary energy source
- Biomass
- Technologies
- Natural Gas Fired Combustion Turbine, Wood/Wood Waste Biomass
- Status
- Operating
This site runs on more than one energy source. EIA-860M capacity splits: Biomass 96 MW, Natural gas 25 MW. It is filed here under Biomass, the source with the most capacity.
Mead Coated Board: FAQ
- Where is Mead Coated Board?
- In Russell County, Alabama (AL). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
- How big is Mead Coated Board?
- 121 MW of nameplate capacity across 3 units, as of the EIA-860M release for 2026-07.
- Who owns Mead Coated Board?
- EIA-860M names Mead Coated Board Inc as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
- Is this the same as Mead Coated Board LLC?
- Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Mead Coated Board Inc here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Mead Coated Board LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
- Is Mead Coated Board still running?
- EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.