Biomass Power Plants in Alabama
Every operating biomass power plant in Alabama on EIA-860M for 2026-07: 11 plants, 22 generating units and 675 MW of nameplate capacity across 10 counties.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Plants
- 11
- 22 generating units
- Nameplate capacity
- 675 MW
- Counties
- 10
- Grid operator
- Mixed
- no single ISO covers a majority
Map of biomass power plants in Alabama
Every one of the 11 plants is drawn at the coordinate EIA files for it.
Loading map…
- Biomass · 11
List of biomass power plants in Alabama
Sort by any column. Capacity is nameplate, summed across every generating unit EIA lists at the site.
| Mead Coated Board2 technologies | Mead Coated Board Inc | Russell | 120.5 | 3 | 1966 | Operating |
| Georgia-Pacific Brewton Mill2 technologies | Georgia-Pacific Brewton LLC | Escambia | 103.4 | 3 | 1964 | Operating |
| International Paper Prattville MillWood/Wood Waste Biomass | International Paper Co | Autauga | 89.8 | 2 | 1967 | Operating |
| Georgia-Pacific Consr Prods LP-NaheolaWood/Wood Waste Biomass | Georgia-Pacific Consr Prods LP-Naheola | Choctaw | 87.5 | 2 | 1993 | Operating |
| International Paper Pine Hill MillWood/Wood Waste Biomass | International Paper Co. | Wilcox | 77.4 | 2 | 1968 | Operating |
| Alabama Pine PulpWood/Wood Waste Biomass | Alabama River Cellulose LLC | Monroe | 69 | 1 | 1991 | Operating |
| Alabama River PulpWood/Wood Waste Biomass | Alabama River Cellulose LLC | Monroe | 48 | 1 | 1978 | Operating |
| WestRock Demopolis MillWood/Wood Waste Biomass | WestRock Mill Company, LLC | Marengo | 47.4 | 2 | 1982 | Operating |
| U S Alliance Coosa PinesWood/Wood Waste Biomass | Bowater Newport Coosa Pines Op | Talladega | 25.9 | 1 | 2007 | Operating |
| Sand Valley Power StationLandfill Gas | Energy Developments, Inc d/b/a EDL | Dekalb | 4.8 | 3 | 2013 | Operating |
| Decatur-Morgan Co LFG Recovery ProjectLandfill Gas | Energy Developments, Inc d/b/a EDL | Morgan | 1.6 | 2 | 2010 | Operating |
Largest biomass power plants in Alabama
- 1Mead Coated BoardRussell County, Alabama120.5 MW
- 2Georgia-Pacific Brewton MillEscambia County, Alabama103.4 MW
- 3International Paper Prattville MillAutauga County, Alabama89.8 MW
- 4Georgia-Pacific Consr Prods LP-NaheolaChoctaw County, Alabama87.5 MW
- 5International Paper Pine Hill MillWilcox County, Alabama77.4 MW
- 6Alabama Pine PulpMonroe County, Alabama69 MW
- 7Alabama River PulpMonroe County, Alabama48 MW
- 8WestRock Demopolis MillMarengo County, Alabama47.4 MW
- 9U S Alliance Coosa PinesTalladega County, Alabama25.9 MW
- 10Sand Valley Power StationDekalb County, Alabama4.8 MW
Biomass power plants by county in Alabama
The county EIA files against each plant. It is the fastest way to find the plant nearest a given town.
| County | Plants | Nameplate MW |
|---|---|---|
| Russell | 1 | 120.5 |
| Monroe | 2 | 117 |
| Escambia | 1 | 103.4 |
| Autauga | 1 | 89.8 |
| Choctaw | 1 | 87.5 |
| Wilcox | 1 | 77.4 |
| Marengo | 1 | 47.4 |
| Talladega | 1 | 25.9 |
| Dekalb | 1 | 4.8 |
| Morgan | 1 | 1.6 |
Biomass Power Plants in Alabama: FAQ
- How many biomass power plants are in Alabama?
- 11, with 675 MW of nameplate capacity between them, spread over 10 counties. That is the EIA-860M operating count for 2026-07.
- Is there a map of Alabama biomass power plants?
- Yes — the map above. Each dot is one biomass power plant, sized by nameplate capacity and placed at the coordinates EIA files for it.
- Which is the largest biomass power plant in Alabama?
- Mead Coated Board, at 121 MW. The table is sorted largest first, so the rest follow it.
- Is there a biomass power plant near me in Alabama?
- The county roll-up below groups every plant by county, which is the quickest way to find the one closest to a given town.
- Which grid operator runs Alabama's biomass power plants?
- No single ISO or RTO covers most of them. EIA files each plant against its own balancing authority, which in Alabama is largely a vertically integrated utility rather than an organised market.
- How current is this, and what is left out?
- EIA-860M for 2026-07. Wood and wood waste, landfill gas, municipal solid waste and other waste biomass. Plants below 1 MW are not surveyed by EIA and so are absent; retirements and additions after 2026-07 arrive with the next monthly release.