Back River Waste Water Treatment

Back River Waste Water Treatment is a 3 MW biomass power plant in Baltimore City County, Maryland, operated by Mayor and City Council of Baltimore City - (MD). It has 3 generating units here, inside PJM. Its units entered service between 2009 and 2012.

As of 2026-07 · updated 2026-07-31 · Source: EIA-860M

Nameplate capacity
3 MW
2.6 MW net summer
Generating units
3
In service
2009–2012
Plant code
59026

Where it is

Loading map…
County
Baltimore City County, Maryland
Coordinates
39.2997, -76.4942
Balancing authority
PJM
Sector
IPP Non-CHP

Units, technology and status

Operator of record
Mayor and City Council of Baltimore City - (MD)
Primary energy source
Biomass
Technologies
Other Waste Biomass, Solar Photovoltaic
Status
Out of service and NOT expected to return to service in next calendar year (2) · Operating (1)

This site runs on more than one energy source. Capacity splits: Biomass 2 MW, Solar 1 MW. It is listed here under Biomass, the energy source with the most capacity.

Back River Waste Water Treatment: FAQ

Where is Back River Waste Water Treatment?
In Baltimore City County, Maryland (MD). The map on this page is placed at the plant's reported coordinates, which locate the site rather than any individual unit.
How big is Back River Waste Water Treatment?
3 MW of nameplate capacity across 3 units, as of 2026-07.
Who owns Back River Waste Water Treatment?
Mayor and City Council of Baltimore City - (MD) is the operator of record. That is not always the ultimate owner.
Is this the same as Back River Waste Water Treatment LLC?
Probably, but the plant data does not say. It records a plant name and an operator — Mayor and City Council of Baltimore City - (MD) here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Back River Waste Water Treatment LLC" usually means this site. This page does not assert a corporate structure it cannot see.
Is Back River Waste Water Treatment still running?
Its status is "Out of service and NOT expected to return to service in next calendar year" as of 2026-07. Statuses change monthly, and this page is updated monthly.