Merrimack is a 496 MW coal power plant in Merrimack County, New Hampshire, operated by Granite Shore Power. EIA-860M lists 4 generating units here, inside ISO New England. Its units entered service between 1960 and 1969.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Nameplate capacity
- 496.4 MW
- 472.1 MW net summer
- Generating units
- 4
- In service
- 1960–1969
- EIA plant ID
- 2364
Where it is
Loading map…
- County
- Merrimack County, New Hampshire
- Coordinates
- 43.1411, -71.4692
- Balancing authority
- ISNE
- Sector
- IPP Non-CHP
Units, technology and status
- Operator of record
- Granite Shore Power
- Primary energy source
- Coal
- Technologies
- Conventional Steam Coal, Petroleum Liquids
- Status
- Operating (3) · Out of service and NOT expected to return to service in next calendar year (1)
This site runs on more than one energy source. EIA-860M capacity splits: Coal 459 MW, Petroleum 37 MW. It is filed here under Coal, the source with the most capacity.
Merrimack: FAQ
- Where is Merrimack?
- In Merrimack County, New Hampshire (NH). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
- How big is Merrimack?
- 496 MW of nameplate capacity across 4 units, as of the EIA-860M release for 2026-07.
- Who owns Merrimack?
- EIA-860M names Granite Shore Power as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
- Is this the same as Merrimack LLC?
- Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Granite Shore Power here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Merrimack LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
- Is Merrimack still running?
- EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.