Pine View Dam

Pine View Dam is a 2 MW hydroelectric power plant in Weber County, Utah, operated by City of Bountiful - (UT). It has 1 generating unit here. Its unit entered service in 1991.

As of 2026-07 · updated 2026-07-31 · Source: EIA-860M

Nameplate capacity
1.8 MW
1.8 MW net summer
Generating units
1
In service
1991
Plant code
7132

Where it is

Loading map…
County
Weber County, Utah
Coordinates
41.2543, -111.8485
Balancing authority
PACE
Sector
Electric Utility

Units, technology and status

Operator of record
City of Bountiful - (UT)
Primary energy source
Hydro
Technologies
Conventional Hydroelectric
Status
Out of service but expected to return to service in next calendar year

Pine View Dam: FAQ

Where is Pine View Dam?
In Weber County, Utah (UT). The map on this page is placed at the plant's reported coordinates, which locate the site rather than any individual unit.
How big is Pine View Dam?
2 MW of nameplate capacity across 1 unit, as of 2026-07.
Who owns Pine View Dam?
City of Bountiful - (UT) is the operator of record. That is not always the ultimate owner.
Is this the same as Pine View Dam LLC?
Probably, but the plant data does not say. It records a plant name and an operator — City of Bountiful - (UT) here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Pine View Dam LLC" usually means this site. This page does not assert a corporate structure it cannot see.
Is Pine View Dam still running?
Its status is "Out of service but expected to return to service in next calendar year" as of 2026-07. Statuses change monthly, and this page is updated monthly.