Northeastern is a 1 GW natural gas power plant in Rogers County, Oklahoma, operated by Public Service Co of Oklahoma. EIA-860M lists 6 generating units here, inside SPP. Its units entered service between 1961 and 2001.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Nameplate capacity
1,477.5 MW
1,302 MW net summer
Generating units
6
In service
1961–2001
EIA plant ID
2963

Where it is

Loading map…
County
Rogers County, Oklahoma
Coordinates
36.4317, -95.7008
Balancing authority
SWPP
Sector
Electric Utility

Units, technology and status

Operator of record
Public Service Co of Oklahoma
Primary energy source
Natural gas
Technologies
Conventional Steam Coal, Natural Gas Fired Combined Cycle, Natural Gas Steam Turbine, Petroleum Liquids
Status
Operating

This site runs on more than one energy source. EIA-860M capacity splits: Natural gas 1 GW, Coal 473 MW, Petroleum 5 MW. It is filed here under Natural gas, the source with the most capacity.

Every plant Public Service Co of Oklahoma reports to EIA →

Northeastern: FAQ

Where is Northeastern?
In Rogers County, Oklahoma (OK). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
How big is Northeastern?
1 GW of nameplate capacity across 6 units, as of the EIA-860M release for 2026-07.
Who owns Northeastern?
EIA-860M names Public Service Co of Oklahoma as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
Is this the same as Northeastern LLC?
Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Public Service Co of Oklahoma here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Northeastern LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
Is Northeastern still running?
EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.