Northeastern is a 1 GW natural gas power plant in Rogers County, Oklahoma, operated by Public Service Co of Oklahoma. EIA-860M lists 6 generating units here, inside SPP. Its units entered service between 1961 and 2001.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Nameplate capacity
- 1,477.5 MW
- 1,302 MW net summer
- Generating units
- 6
- In service
- 1961–2001
- EIA plant ID
- 2963
Where it is
Loading map…
- County
- Rogers County, Oklahoma
- Coordinates
- 36.4317, -95.7008
- Balancing authority
- SWPP
- Sector
- Electric Utility
Units, technology and status
- Operator of record
- Public Service Co of Oklahoma
- Primary energy source
- Natural gas
- Technologies
- Conventional Steam Coal, Natural Gas Fired Combined Cycle, Natural Gas Steam Turbine, Petroleum Liquids
- Status
- Operating
This site runs on more than one energy source. EIA-860M capacity splits: Natural gas 1 GW, Coal 473 MW, Petroleum 5 MW. It is filed here under Natural gas, the source with the most capacity.
Northeastern: FAQ
- Where is Northeastern?
- In Rogers County, Oklahoma (OK). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
- How big is Northeastern?
- 1 GW of nameplate capacity across 6 units, as of the EIA-860M release for 2026-07.
- Who owns Northeastern?
- EIA-860M names Public Service Co of Oklahoma as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
- Is this the same as Northeastern LLC?
- Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Public Service Co of Oklahoma here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Northeastern LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
- Is Northeastern still running?
- EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.