Brunot Island
Brunot Island is a 365 MW natural gas power plant in Allegheny County, Pennsylvania, operated by Brunot Island Power, LLC. EIA-860M lists 5 generating units here, inside PJM. Its units entered service between 1972 and 1974.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Nameplate capacity
- 365.4 MW
- 261.6 MW net summer
- Generating units
- 5
- In service
- 1972–1974
- EIA plant ID
- 3096
Where it is
Loading map…
- County
- Allegheny County, Pennsylvania
- Coordinates
- 40.4649, -80.0438
- Balancing authority
- PJM
- Sector
- IPP Non-CHP
Units, technology and status
- Operator of record
- Brunot Island Power, LLC
- Primary energy source
- Natural gas
- Technologies
- Natural Gas Fired Combined Cycle, Petroleum Liquids
- Status
- Operating
This site runs on more than one energy source. EIA-860M capacity splits: Natural gas 340 MW, Petroleum 26 MW. It is filed here under Natural gas, the source with the most capacity.
Brunot Island: FAQ
- Where is Brunot Island?
- In Allegheny County, Pennsylvania (PA). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
- How big is Brunot Island?
- 365 MW of nameplate capacity across 5 units, as of the EIA-860M release for 2026-07.
- Who owns Brunot Island?
- EIA-860M names Brunot Island Power, LLC as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
- Is this the same as Brunot Island LLC?
- Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Brunot Island Power, LLC here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "Brunot Island LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
- Is Brunot Island still running?
- EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.