Planned battery storage projects in Nevada
What is planned in Nevada as of 2026-07: 10 battery storage projects totalling 6 GW, each with the in-service year its developer reported and its construction status. A planned project is not a built one.
As of 2026-07 · updated 2026-07-31 · Source: EIA-860M
- Planned projects
- 10
- 18 generating units
- Proposed capacity
- 6 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2029
Map of planned battery storage projects in Nevada
Loading map…
List of planned battery storage projects in Nevada
| Libra Solar2 technologies | Libra Solar LLC | Lyon | 1,400 | 2 | 2027 | Under construction |
|---|---|---|---|---|---|---|
| Sierra Solar Hybrid2 technologies | Sierra Pacific Power Co | Churchill | 800 | 2 | 2026 | Regulatory approvals pending. Not under construction |
| Purple Sage Energy Center2 technologies | Noble Solar LLC | Clark | 800 | 2 | 2028 | Planned for installation |
| Arida Solar (Hybrid)2 technologies | 326FW 8me LLC | Clark | 740 | 2 | 2029 | Planned for installation |
| Southern Bighorn Solar Hybrid2 technologies | 300MS 8me LLC | Clark | 600 | 2 | 2028 | Planned for installation |
| Robinson Solar2 technologies | Repsol Renewables NA | White Pine | 600 | 2 | 2029 | Planned for installation |
| Vitex StorageBatteries | Cypress Creek Renewables | Clark | 300 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| Boulder Solar III LLC2 technologies | 174 Power Global Corp. | Clark | 256 | 2 | 2027 | Planned for installation |
| Southern Bighorn Solar 22 technologies | 425LM 8ME LLC | Clark | 200 | 2 | 2028 | Regulatory approvals pending. Not under construction |
| Roccasecca BESS LLCBatteries | Roccasecca BESS LLC | Clark | 126.5 | 1 | 2027 | Under construction |
Where they are in the build
- Planned for installation5
- Regulatory approvals pending. Not under construction3
- Under construction1
- Under construction1
Planned battery storage projects in Nevada: FAQ
- How many battery storage projects are planned in Nevada?
- 10, for 6 GW of nameplate capacity. These are generators developers have reported as planned, not generators that exist.
- What do the status letters mean?
- Each planned generator carries a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. Projects are canceled or postponed, and move in and out of the planned list month to month. This page lists what was planned as of 2026-07 and nothing more.