Planned battery storage projects in Washington

What EIA-860M's Planned sheet says is coming in Washington: 7 battery storage projects totalling 3 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
7
11 generating units
Proposed capacity
3 GW
Earliest in-service year
2026
Latest in-service year
2031

Map of planned battery storage projects in Washington

Loading map…

List of planned battery storage projects in Washington

Planned battery storage projects in Washington
Hop Hill Solar Generation and BESS3 technologiesHOHI bn, LLCBenton1,20032031Regulatory approvals pending. Not under construction
Lower Snake Solar Generation BESS2 technologiesLOSN, LLCGarfield60022029Regulatory approvals pending. Not under construction
Royal Slope2 technologiesRoyal Slope Solar LLCGrant52022027Regulatory approvals received. Not under construction
Centralia Battery Energy Storage SystemBatteriesCENT bn, LLCThurston20012028Regulatory approvals pending. Not under construction
Greenwater BESSBatteriesGREE bn, LLCPierce20012026Under construction
AGATE BESSBatteriesBrightNight PowerKitsap17012029Regulatory approvals pending. Not under construction
Arlington Battery Energy Storage SystemBatteriesPUD No 1 of Snohomish County - (WA)Snohomish2512026Under construction

Where they are in the build

  • Regulatory approvals pending. Not under construction4
  • Regulatory approvals received. Not under construction1
  • Under construction1
  • Under construction1

Planned battery storage projects in Washington: FAQ

How many battery storage projects are planned in Washington?
7, for 3 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.