Planned natural gas power plants in California

What EIA-860M's Planned sheet says is coming in California: 2 natural gas power plants totalling 114 MW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
2
9 generating units
Proposed capacity
114 MW
Earliest in-service year
2029
Latest in-service year
2030

Map of planned natural gas power plants in California

Loading map…

List of planned natural gas power plants in California

Planned natural gas power plants in California
El Centro HybridNatural Gas Internal Combustion EngineImperial Irrigation DistrictImperial112.862029Planned for installation
Energy CenterNatural Gas Fired Combustion TurbineUniversity of RedlandsSan Bernardino0.932030Planned for installation

Where they are in the build

  • Planned for installation2

Planned natural gas power plants in California: FAQ

How many natural gas power plants are planned in California?
2, for 114 MW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.