Planned solar farms in Arizona

What EIA-860M's Planned sheet says is coming in Arizona: 12 solar farms totalling 3 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
12
14 generating units
Proposed capacity
3 GW
Earliest in-service year
2026
Latest in-service year
2030

Map of planned solar farms in Arizona

Loading map…

List of planned solar farms in Arizona

Planned solar farms in Arizona
Red Antelope Solar & Energy Storage Farm2 technologies302PN 8me LLCCoconino70022028Planned for installation
Elisabeth SolarSolar PhotovoltaicLeeward Asset Management, LLCYuma35012028Regulatory approvals pending. Not under construction
AtlasSolar Photovoltaic174 Power Global Corp.La Paz30012026Under construction
ATLAS SOLAR IVSolar PhotovoltaicATLAS SOLAR IV, LLCLa Paz30012027Under construction
Centennial Flats2 technologiesCopia PowerLa Paz255.722026Under construction
ATLAS Solar X, LLCSolar PhotovoltaicATLAS Solar Manager, LLCLa Paz22512027Planned for installation
La Paz Solar TowerSolar Thermal without Energy StorageEnviromission, IncLa Paz20012030Planned for installation
ATLAS Solar XI, LLCSolar PhotovoltaicATLAS Solar Manager, LLCLa Paz20012027Planned for installation
Ironwood SolarSolar PhotovoltaicArizona Public Service CoYuma16812026Construction complete
ATLAS IISolar PhotovoltaicATLAS Solar II, LLCLa Paz10012026Under construction
ATLAS Solar VI, LLCSolar PhotovoltaicATLAS Solar VI, LLCLa Paz10012026Under construction
Sierra SolarSolar PhotovoltaicSierra Solar LLCMohave2512027Regulatory approvals received. Not under construction

Where they are in the build

  • Planned for installation4
  • Under construction3
  • Under construction2
  • Regulatory approvals pending. Not under construction1
  • Construction complete1
  • Regulatory approvals received. Not under construction1

Planned solar farms in Arizona: FAQ

How many solar farms are planned in Arizona?
12, for 3 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.