Planned solar farms in Arizona
What EIA-860M's Planned sheet says is coming in Arizona: 12 solar farms totalling 3 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Planned projects
- 12
- 14 generating units
- Proposed capacity
- 3 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2030
Map of planned solar farms in Arizona
Loading map…
List of planned solar farms in Arizona
| Red Antelope Solar & Energy Storage Farm2 technologies | 302PN 8me LLC | Coconino | 700 | 2 | 2028 | Planned for installation |
| Elisabeth SolarSolar Photovoltaic | Leeward Asset Management, LLC | Yuma | 350 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| AtlasSolar Photovoltaic | 174 Power Global Corp. | La Paz | 300 | 1 | 2026 | Under construction |
| ATLAS SOLAR IVSolar Photovoltaic | ATLAS SOLAR IV, LLC | La Paz | 300 | 1 | 2027 | Under construction |
| Centennial Flats2 technologies | Copia Power | La Paz | 255.7 | 2 | 2026 | Under construction |
| ATLAS Solar X, LLCSolar Photovoltaic | ATLAS Solar Manager, LLC | La Paz | 225 | 1 | 2027 | Planned for installation |
| La Paz Solar TowerSolar Thermal without Energy Storage | Enviromission, Inc | La Paz | 200 | 1 | 2030 | Planned for installation |
| ATLAS Solar XI, LLCSolar Photovoltaic | ATLAS Solar Manager, LLC | La Paz | 200 | 1 | 2027 | Planned for installation |
| Ironwood SolarSolar Photovoltaic | Arizona Public Service Co | Yuma | 168 | 1 | 2026 | Construction complete |
| ATLAS IISolar Photovoltaic | ATLAS Solar II, LLC | La Paz | 100 | 1 | 2026 | Under construction |
| ATLAS Solar VI, LLCSolar Photovoltaic | ATLAS Solar VI, LLC | La Paz | 100 | 1 | 2026 | Under construction |
| Sierra SolarSolar Photovoltaic | Sierra Solar LLC | Mohave | 25 | 1 | 2027 | Regulatory approvals received. Not under construction |
Where they are in the build
- Planned for installation4
- Under construction3
- Under construction2
- Regulatory approvals pending. Not under construction1
- Construction complete1
- Regulatory approvals received. Not under construction1
Planned solar farms in Arizona: FAQ
- How many solar farms are planned in Arizona?
- 12, for 3 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
- What do the status letters mean?
- EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.