Planned solar farms in Colorado
What EIA-860M's Planned sheet says is coming in Colorado: 31 solar farms totalling 2 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Planned projects
- 31
- 32 generating units
- Proposed capacity
- 2 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2030
Map of planned solar farms in Colorado
Loading map…
List of planned solar farms in Colorado
| Mirasol Energy Center, LLC.Solar Photovoltaic | Mirasol Energy Center, LLC | Pueblo | 400 | 1 | 2028 | Regulatory approvals received. Not under construction |
| Arroyo SolarSolar Photovoltaic | Public Service Co of Colorado | Pueblo | 335 | 1 | 2026 | Under construction |
| Deep Space SolarSolar Photovoltaic | Deep Space Solar LLC | Kiowa | 300 | 1 | 2030 | Planned for installation |
| Stagecoach LRESolar Photovoltaic | Leeward Asset Management, LLC | Pueblo | 230 | 1 | 2029 | Regulatory approvals received. Not under construction |
| Turkey Creek Solar ProjectSolar Photovoltaic | 174 Power Global Corp. | Pueblo | 200 | 1 | 2027 | Planned for installation |
| Elk RunSolar Photovoltaic | Cypress Creek Renewables | Las Animas | 200 | 1 | 2029 | Regulatory approvals pending. Not under construction |
| Thunder Wolf II, LLCSolar Photovoltaic | Thunder Wolf II, LLC | Pueblo | 200 | 1 | 2027 | Regulatory approvals received. Not under construction |
| South Platte SolarSolar Photovoltaic | South Platte Solar | Morgan | 150 | 1 | 2027 | Under construction |
| Canyonland SolarSolar Photovoltaic | Canyonland Solar LLC | Montezuma | 140 | 1 | 2027 | Planned for installation |
| Sundance (CO)2 technologies | Cypress Creek Renewables | Elbert | 124.9 | 2 | 2026 | Under construction |
| Black Hollow SunSolar Photovoltaic | Contour Global | Weld | 107 | 1 | 2026 | Under construction |
| KeenesburgSolar Photovoltaic | ENGIE Distributed Renewables Development LLC | Weld | 7.2 | 1 | 2026 | Under construction |
| Raceway Solar - (CO)Solar Photovoltaic | Raceway Solar, LLC | Morgan | 7 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Pivot Solar 36Solar Photovoltaic | Pivot Energy | Weld | 5 | 1 | 2027 | Under construction |
| Pivot Solar 33 LLCSolar Photovoltaic | Pivot Energy | Weld | 5 | 1 | 2027 | Under construction |
| La Junta SolarSolar Photovoltaic | Clay Creek Energy, LLC | Otero | 4.8 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Lamar SolarSolar Photovoltaic | Clay Creek Energy, LLC | Prowers | 4.8 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Pivot Solar 58 LLCSolar Photovoltaic | Pivot Energy | Weld | 4.5 | 1 | 2026 | Under construction |
| Waterton Solar ISolar Photovoltaic | Public Service Co of Colorado | Douglas | 4 | 1 | 2026 | Under construction |
| Waterton Solar IISolar Photovoltaic | Public Service Co of Colorado | Douglas | 4 | 1 | 2026 | Under construction |
| Pivot Solar 53 LLCSolar Photovoltaic | Pivot Energy | Adams | 4 | 1 | 2026 | Under construction |
| Pivot Solar 50 LLCSolar Photovoltaic | Pivot Energy | Weld | 4 | 1 | 2026 | Under construction |
| Pivot Solar 56 LLCSolar Photovoltaic | Pivot Energy | Weld | 3.6 | 1 | 2027 | Under construction |
| Pivot Solar 43 LLCSolar Photovoltaic | Pivot Energy | Adams | 3.5 | 1 | 2026 | Under construction |
| Waxwing Solar CSGSolar Photovoltaic | Waxwing Solar | Pueblo | 3 | 1 | 2027 | Under construction |
| Pivot Solar 57 LLCSolar Photovoltaic | Pivot Energy | Mesa | 2 | 1 | 2026 | Under construction |
| Pivot Solar 42 LLCSolar Photovoltaic | Pivot Energy | Larimer | 1.9 | 1 | 2026 | Under construction |
| Fort Lyon SolarSolar Photovoltaic | Clay Creek Energy, LLC | Bent | 1.8 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Trinidad SolarSolar Photovoltaic | Clay Creek Energy, LLC | Las Animas | 1.8 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Pivot Solar 71 LLCSolar Photovoltaic | Pivot Energy | Morgan | 1.8 | 1 | 2026 | Under construction |
| Pivot Solar 60 LLCSolar Photovoltaic | Pivot Energy | Weld | 1.1 | 1 | 2026 | Under construction |
Where they are in the build
- Under construction12
- Under construction7
- Regulatory approvals pending. Not under construction6
- Regulatory approvals received. Not under construction3
- Planned for installation3
Planned solar farms in Colorado: FAQ
- How many solar farms are planned in Colorado?
- 31, for 2 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
- What do the status letters mean?
- EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.