Planned solar farms in Colorado

What EIA-860M's Planned sheet says is coming in Colorado: 31 solar farms totalling 2 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
31
32 generating units
Proposed capacity
2 GW
Earliest in-service year
2026
Latest in-service year
2030

Map of planned solar farms in Colorado

Loading map…

List of planned solar farms in Colorado

Planned solar farms in Colorado
Mirasol Energy Center, LLC.Solar PhotovoltaicMirasol Energy Center, LLCPueblo40012028Regulatory approvals received. Not under construction
Arroyo SolarSolar PhotovoltaicPublic Service Co of ColoradoPueblo33512026Under construction
Deep Space SolarSolar PhotovoltaicDeep Space Solar LLCKiowa30012030Planned for installation
Stagecoach LRESolar PhotovoltaicLeeward Asset Management, LLCPueblo23012029Regulatory approvals received. Not under construction
Turkey Creek Solar ProjectSolar Photovoltaic174 Power Global Corp.Pueblo20012027Planned for installation
Elk RunSolar PhotovoltaicCypress Creek RenewablesLas Animas20012029Regulatory approvals pending. Not under construction
Thunder Wolf II, LLCSolar PhotovoltaicThunder Wolf II, LLCPueblo20012027Regulatory approvals received. Not under construction
South Platte SolarSolar PhotovoltaicSouth Platte SolarMorgan15012027Under construction
Canyonland SolarSolar PhotovoltaicCanyonland Solar LLCMontezuma14012027Planned for installation
Sundance (CO)2 technologiesCypress Creek RenewablesElbert124.922026Under construction
Black Hollow SunSolar PhotovoltaicContour GlobalWeld10712026Under construction
KeenesburgSolar PhotovoltaicENGIE Distributed Renewables Development LLCWeld7.212026Under construction
Raceway Solar - (CO)Solar PhotovoltaicRaceway Solar, LLCMorgan712027Regulatory approvals pending. Not under construction
Pivot Solar 36Solar PhotovoltaicPivot EnergyWeld512027Under construction
Pivot Solar 33 LLCSolar PhotovoltaicPivot EnergyWeld512027Under construction
La Junta SolarSolar PhotovoltaicClay Creek Energy, LLCOtero4.812027Regulatory approvals pending. Not under construction
Lamar SolarSolar PhotovoltaicClay Creek Energy, LLCProwers4.812027Regulatory approvals pending. Not under construction
Pivot Solar 58 LLCSolar PhotovoltaicPivot EnergyWeld4.512026Under construction
Waterton Solar ISolar PhotovoltaicPublic Service Co of ColoradoDouglas412026Under construction
Waterton Solar IISolar PhotovoltaicPublic Service Co of ColoradoDouglas412026Under construction
Pivot Solar 53 LLCSolar PhotovoltaicPivot EnergyAdams412026Under construction
Pivot Solar 50 LLCSolar PhotovoltaicPivot EnergyWeld412026Under construction
Pivot Solar 56 LLCSolar PhotovoltaicPivot EnergyWeld3.612027Under construction
Pivot Solar 43 LLCSolar PhotovoltaicPivot EnergyAdams3.512026Under construction
Waxwing Solar CSGSolar PhotovoltaicWaxwing SolarPueblo312027Under construction
Pivot Solar 57 LLCSolar PhotovoltaicPivot EnergyMesa212026Under construction
Pivot Solar 42 LLCSolar PhotovoltaicPivot EnergyLarimer1.912026Under construction
Fort Lyon SolarSolar PhotovoltaicClay Creek Energy, LLCBent1.812027Regulatory approvals pending. Not under construction
Trinidad SolarSolar PhotovoltaicClay Creek Energy, LLCLas Animas1.812027Regulatory approvals pending. Not under construction
Pivot Solar 71 LLCSolar PhotovoltaicPivot EnergyMorgan1.812026Under construction
Pivot Solar 60 LLCSolar PhotovoltaicPivot EnergyWeld1.112026Under construction

Where they are in the build

  • Under construction12
  • Under construction7
  • Regulatory approvals pending. Not under construction6
  • Regulatory approvals received. Not under construction3
  • Planned for installation3

Planned solar farms in Colorado: FAQ

How many solar farms are planned in Colorado?
31, for 2 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.