Planned solar farms in Connecticut

What EIA-860M's Planned sheet says is coming in Connecticut: 5 solar farms totalling 300 MW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
5
6 generating units
Proposed capacity
300 MW
Earliest in-service year
2026
Latest in-service year
2028

Map of planned solar farms in Connecticut

Loading map…

List of planned solar farms in Connecticut

Planned solar farms in Connecticut
Broadleaf SolarSolar PhotovoltaicBroadleaf Solar, LLCHartford20012028Regulatory approvals pending. Not under construction
Pure Hedge LLC2 technologiesPure Hedge LLCWindham9022027Under construction
CT Airport Authority Solar OneSolar PhotovoltaicCAA CT Solar One, LLCHartford412027Planned for installation
Putnam Meadow Solar StationSolar PhotovoltaicPutnam Meadow Solar Station, LLCWindham412027Regulatory approvals pending. Not under construction
Windsor LocksSolar PhotovoltaicENGIE Distributed Renewables Development LLCHartford1.812026Under construction

Where they are in the build

  • Regulatory approvals pending. Not under construction2
  • Under construction2
  • Planned for installation1

Planned solar farms in Connecticut: FAQ

How many solar farms are planned in Connecticut?
5, for 300 MW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.