Planned solar farms in Florida

What EIA-860M's Planned sheet says is coming in Florida: 24 solar farms totalling 2 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
24
25 generating units
Proposed capacity
2 GW
Earliest in-service year
2026
Latest in-service year
2029

Map of planned solar farms in Florida

Loading map…

List of planned solar farms in Florida

Planned solar farms in Florida
FRP Miller Solar2 technologiesFRP Miller Solar LLCDuval124.522026Under construction
Caverns SolarSolar PhotovoltaicCVSO, LLCJackson7512029Regulatory approvals pending. Not under construction
Highland Solar NorthSolar PhotovoltaicPlacid Solar II, LLCHighlands74.912027Regulatory approvals pending. Not under construction
Highland Solar SouthSolar PhotovoltaicPlacid Solar, LLCHighlands74.912026Under construction
Bailey Mill SolarSolar PhotovoltaicDuke Energy Florida, LLCJefferson74.912026Under construction
Lonesome Camp Solar PlantSolar PhotovoltaicDuke Energy Florida, LLCOsceola74.912027Under construction
Turnpike Solar PlantSolar PhotovoltaicDuke Energy Florida, LLCOsceola74.912027Under construction
Middle LakeSolar PhotovoltaicFlorida Power & Light CoMadison74.512027Under construction
PineconeSolar PhotovoltaicFlorida Power & Light CoCalhoun74.512027Under construction
SaddleSolar PhotovoltaicFlorida Power & Light CoCalhoun74.512027Under construction
Spanish MossSolar PhotovoltaicFlorida Power & Light CoSt Lucie74.512027Under construction
TangeloSolar PhotovoltaicFlorida Power & Light CoOkeechobee74.512027Under construction
AmbersweetSolar PhotovoltaicFlorida Power & Light CoIndian River74.512027Under construction
CatfishSolar PhotovoltaicFlorida Power & Light CoOkeechobee74.512027Under construction
CocoplumSolar PhotovoltaicFlorida Power & Light CoHendry74.512027Under construction
County LineSolar PhotovoltaicFlorida Power & Light CoDeSoto74.512027Under construction
Hardwood HammockSolar PhotovoltaicFlorida Power & Light CoWalton74.512027Under construction
HendrySolar PhotovoltaicFlorida Power & Light CoHendry74.512027Under construction
Joshua CreekSolar PhotovoltaicFlorida Power & Light CoDeSoto74.512027Under construction
Maple TrailSolar PhotovoltaicFlorida Power & Light CoBaker74.512027Under construction
Keene Branch SolarSolar PhotovoltaicTampa Electric CoHillsborough74.512026Under construction
Mattaniah SolarSolar PhotovoltaicTampa Electric CoPolk5212026Under construction
FRP Forest Trail SolarSolar PhotovoltaicFRP Forest Trail Solar LLCDuval5012026Under construction
Brewster SolarSolar PhotovoltaicTampa Electric CoPolk42.712026Under construction

Where they are in the build

  • Under construction18
  • Under construction4
  • Regulatory approvals pending. Not under construction2

Planned solar farms in Florida: FAQ

How many solar farms are planned in Florida?
24, for 2 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.