Planned solar farms in Georgia
What is planned in Georgia as of 2026-07: 15 solar farms totalling 4 GW, each with the in-service year its developer reported and its construction status. A planned project is not a built one.
As of 2026-07 · updated 2026-07-31 · Source: EIA-860M
- Planned projects
- 15
- 17 generating units
- Proposed capacity
- 4 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2030
Map of planned solar farms in Georgia
Loading map…
List of planned solar farms in Georgia
| Pepper Hammock Solar and Storage2 technologies | BrightNight Power | Wayne | 2,500 | 3 | 2029 | Regulatory approvals pending. Not under construction |
|---|---|---|---|---|---|---|
| Peach Wood SolarSolar Photovoltaic | Peach WoodSolar LLC | Mitchell | 261 | 1 | 2030 | Planned for installation |
| Rock House SolarSolar Photovoltaic | EDF Renewables Development, Inc. | McDuffie | 250 | 1 | 2027 | Planned for installation |
| Conez Solar, LLCSolar Photovoltaic | Samsung C&T Renewables, LLC | Emanuel | 150 | 1 | 2027 | Planned for installation |
| Crossroads Solar - GASolar Photovoltaic | Crossroads bn, LLC | Liberty | 150 | 1 | 2029 | Regulatory approvals pending. Not under construction |
| Laurens SolarSolar Photovoltaic | Laurens Solar I, LLC | Laurens | 150 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| SR Bacon IISolar Photovoltaic | SR Bacon II, LLC | Bacon | 115 | 1 | 2027 | Regulatory approvals received. Not under construction |
| SR NorwoodSolar Photovoltaic | SR Norwood, LLC | Warren | 107 | 1 | 2027 | Regulatory approvals received. Not under construction |
| SR Bacon IIISolar Photovoltaic | SR Bacon III, LLC | Bacon | 100 | 1 | 2027 | Regulatory approvals received. Not under construction |
| SR Rochelle ISolar Photovoltaic | SR Rochelle I, LLC | Wilcox | 90 | 1 | 2026 | Under construction |
| SR BaconSolar Photovoltaic | SR Bacon, LLC | Bacon | 85 | 1 | 2026 | Under construction |
| Drawhorn SolarSolar Photovoltaic | Drawhorn Solar, LLC | Hancock | 80 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Alligator Creek SolarSolar Photovoltaic | Alligator Creek Solar, LLC | Wheeler | 80 | 1 | 2026 | Under construction |
| Sandersville SolarSolar Photovoltaic | Sandersville Solar, LLC | Washington | 50 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| SR Rochelle IISolar Photovoltaic | SR Rochelle II, LLC | Wilcox | 50 | 1 | 2027 | Regulatory approvals received. Not under construction |
Where they are in the build
- Regulatory approvals pending. Not under construction5
- Regulatory approvals received. Not under construction4
- Planned for installation3
- Under construction3
Planned solar farms in Georgia: FAQ
- How many solar farms are planned in Georgia?
- 15, for 4 GW of nameplate capacity. These are generators developers have reported as planned, not generators that exist.
- What do the status letters mean?
- Each planned generator carries a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. Projects are canceled or postponed, and move in and out of the planned list month to month. This page lists what was planned as of 2026-07 and nothing more.