Planned solar farms in Massachusetts

What EIA-860M's Planned sheet says is coming in Massachusetts: 5 solar farms totalling 26 MW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
5
6 generating units
Proposed capacity
26 MW
Earliest in-service year
2026
Latest in-service year
2027

Map of planned solar farms in Massachusetts

Loading map…

List of planned solar farms in Massachusetts

Planned solar farms in Massachusetts
MA Acushnet 540R Main St2 technologiesTJA 540R Main St. Acushnet, LLCBristol622027Regulatory approvals pending. Not under construction
Sturbridge Road SolarSolar PhotovoltaicMadison Energy Investments LLCWorcester512026Construction complete
Clems Way SolarSolar PhotovoltaicReWild Renewables, LLCBristol512027Regulatory approvals received. Not under construction
Logging Swamp NorthSolar PhotovoltaicReWild Renewables, LLCPlymouth512027Regulatory approvals received. Not under construction
Logging Swamp SouthSolar PhotovoltaicReWild Renewables, LLCPlymouth512027Regulatory approvals received. Not under construction

Where they are in the build

  • Regulatory approvals received. Not under construction3
  • Regulatory approvals pending. Not under construction1
  • Construction complete1

Planned solar farms in Massachusetts: FAQ

How many solar farms are planned in Massachusetts?
5, for 26 MW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.