Planned solar farms in Ohio
What is planned in Ohio as of 2026-07: 20 solar farms totalling 3 GW, each with the in-service year its developer reported and its construction status. A planned project is not a built one.
As of 2026-07 · updated 2026-07-31 · Source: EIA-860M
- Planned projects
- 20
- 20 generating units
- Proposed capacity
- 3 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2028
Map of planned solar farms in Ohio
Loading map…
List of planned solar farms in Ohio
| Harvey SolarSolar Photovoltaic | Leeward Asset Management, LLC | Licking | 350 | 1 | 2028 | Regulatory approvals received. Not under construction |
|---|---|---|---|---|---|---|
| Yellow Wood Solar Energy LLCSolar Photovoltaic | Invenergy Services LLC | Clinton | 300 | 1 | 2027 | Under construction |
| Eastern Cottontail SolarSolar Photovoltaic | EDF Renewables Development, Inc. | Fairfield | 220 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| Henry SolarSolar Photovoltaic | Repsol Renewables NA | Henry | 206 | 1 | 2028 | Planned for installation |
| Palomino SolarSolar Photovoltaic | Palomino Solar, LLC | Highland | 200 | 1 | 2027 | Under construction |
| Pleasant Prairie Solar Energy LLCSolar Photovoltaic | Invenergy Services LLC | Franklin | 200 | 1 | 2026 | Under construction |
| Ritter SolarSolar Photovoltaic | Repsol Renewables NA | Fulton | 199 | 1 | 2027 | Planned for installation |
| Kingwood SolarSolar Photovoltaic | Vesper Energy Development LLC | Greene | 175 | 1 | 2027 | Planned for installation |
| Springwater Solar, LLCSolar Photovoltaic | Springwater Solar, LLC | Madison | 155 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Stark Solar, LLCSolar Photovoltaic | Samsung C&T Renewables, LLC | Stark | 150 | 1 | 2027 | Planned for installation |
| Border Basin SolarSolar Photovoltaic | Border Basin, LLC | Hancock | 120 | 1 | 2026 | Under construction |
| South Branch SolarSolar Photovoltaic | Leeward Asset Management, LLC | Hancock | 115 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Union Ridge SolarSolar Photovoltaic | RWE Clean Energy | Montgomery | 108 | 1 | 2026 | Construction complete |
| Nottingham SolarSolar Photovoltaic | BQ Energy Development | Harrison | 100 | 1 | 2026 | Under construction |
| Ripley SolarSolar Photovoltaic | Cypress Creek Renewables | Fairfield | 100 | 1 | 2027 | Planned for installation |
| Mark Center Solar ProjectSolar Photovoltaic | Naturgy Solar Operation USA LLC | Defiance | 90 | 1 | 2026 | Under construction |
| Juliet Energy Project, LLCSolar Photovoltaic | Lightsource Renewable Energy Asset Management, LLC | Wood | 50 | 1 | 2026 | Construction complete |
| Great Bear Solar, LLCSolar Photovoltaic | Avangrid Power LLC | Van Wert | 46 | 1 | 2027 | Planned for installation |
| Steubenville SolarSolar Photovoltaic | BQ Energy Development | Jefferson | 43 | 1 | 2027 | Planned for installation |
| Trenton Solar - (OH)Solar Photovoltaic | ENGIE Distributed Renewables Development LLC | Butler | 9.5 | 1 | 2027 | Under construction |
Where they are in the build
- Planned for installation7
- Under construction5
- Regulatory approvals pending. Not under construction3
- Under construction2
- Construction complete2
- Regulatory approvals received. Not under construction1
Planned solar farms in Ohio: FAQ
- How many solar farms are planned in Ohio?
- 20, for 3 GW of nameplate capacity. These are generators developers have reported as planned, not generators that exist.
- What do the status letters mean?
- Each planned generator carries a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. Projects are canceled or postponed, and move in and out of the planned list month to month. This page lists what was planned as of 2026-07 and nothing more.