Planned solar farms in Oklahoma

What EIA-860M's Planned sheet says is coming in Oklahoma: 10 solar farms totalling 2 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
10
10 generating units
Proposed capacity
2 GW
Earliest in-service year
2026
Latest in-service year
2027

Map of planned solar farms in Oklahoma

Loading map…

List of planned solar farms in Oklahoma

Planned solar farms in Oklahoma
High Spring Solar EnergySolar PhotovoltaicHigh Spring Solar EnergyMuskogee40012027Planned for installation
Rumble SolarSolar PhotovoltaicRumble Solar, LLCGrady25012026Under construction
Twelvemile Solar 3Solar PhotovoltaicLeeward Asset Management, LLCMayes20012026Under construction
Rush Springs SolarSolar PhotovoltaicRush Springs Solar, LLCStephens20012026Under construction
Panhandle SolarSolar PhotovoltaicPanhandle Solar, LLCTexas10212026Under construction
Mayes County SolarSolar PhotovoltaicLeeward Asset Management, LLCMayes101.512026Under construction
Choctaw Fields Solar ProjectSolar PhotovoltaicChoctaw Fields Solar Project, LLCChoctaw8512026Construction complete
Fiddle Leaf Solar, LLCSolar PhotovoltaicLightsource Renewable Energy Asset Management, LLCDelaware8012027Regulatory approvals received. Not under construction
Saltbranch Solar 1Solar PhotovoltaicLeeward Asset Management, LLCMayes7312026Under construction
Saltbranch 2Solar PhotovoltaicLeeward Asset Management, LLCMayes7312026Under construction

Where they are in the build

  • Under construction5
  • Under construction2
  • Planned for installation1
  • Construction complete1
  • Regulatory approvals received. Not under construction1

Planned solar farms in Oklahoma: FAQ

How many solar farms are planned in Oklahoma?
10, for 2 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.