Planned solar farms in South Carolina
What is planned in South Carolina as of 2026-07: 23 solar farms totalling 2 GW, each with the in-service year its developer reported and its construction status. A planned project is not a built one.
As of 2026-07 · updated 2026-07-31 · Source: EIA-860M
- Planned projects
- 23
- 23 generating units
- Proposed capacity
- 2 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2029
Map of planned solar farms in South Carolina
Loading map…
List of planned solar farms in South Carolina
| Kingstree East 230 Solar ProjectSolar Photovoltaic | Kingstree East 230 LLC | Georgetown | 249 | 1 | 2029 | Regulatory approvals received. Not under construction |
|---|---|---|---|---|---|---|
| SR CordovaSolar Photovoltaic | SR Cordova, LLC | Orangeburg | 100 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Robinson Solar PlantSolar Photovoltaic | Duke Energy Carolinas, LLC | Chesterfield | 76 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Lotus SolarSolar Photovoltaic | Lotus Solar LLC | Darlington | 75 | 1 | 2027 | Regulatory approvals received. Not under construction |
| B & K SolarSolar Photovoltaic | B & K Solar | Darlington | 74.9 | 1 | 2026 | Under construction |
| Colleton SolarSolar Photovoltaic | Colleton Solar | Colleton | 74.9 | 1 | 2028 | Regulatory approvals received. Not under construction |
| Culpepper SolarSolar Photovoltaic | Culpepper Solar | Darlington | 74.9 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Juniper SolarSolar Photovoltaic | Juniper Solar | Chesterfield | 74.9 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Rollins SolarSolar Photovoltaic | Rollins Solar | Darlington | 74.9 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Ross SolarSolar Photovoltaic | Ross Solar | Darlington | 74.9 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Kingstree West 115Solar Photovoltaic | Kingstree West 115 LLC | Williamsburg | 74.9 | 1 | 2026 | Construction complete |
| Holliday Solar ISolar Photovoltaic | Holliday Solar I | Horry | 74 | 1 | 2028 | Regulatory approvals received. Not under construction |
| Shining Sun SolarSolar Photovoltaic | Shining Sun Solar | Orangeburg | 74 | 1 | 2028 | Regulatory approvals received. Not under construction |
| Hudson Place Solar PlantSolar Photovoltaic | Duke Energy Carolinas, LLC | Newberry | 70.7 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| Melsam SolarSolar Photovoltaic | Melsam Solar | Dillon | 65 | 1 | 2028 | Regulatory approvals received. Not under construction |
| Shorthorn SolarSolar Photovoltaic | Shorthorn Solar | Lee | 60 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Crossroads SolarSolar Photovoltaic | Crossroads Solar | Barnwell | 50 | 1 | 2028 | Regulatory approvals received. Not under construction |
| GEB SolarSolar Photovoltaic | GEB Solar | Darlington | 50 | 1 | 2028 | Regulatory approvals received. Not under construction |
| Quest SolarSolar Photovoltaic | Quest Solar | Allendale | 50 | 1 | 2028 | Regulatory approvals received. Not under construction |
| SR GeorgetownSolar Photovoltaic | SR Georgetown. LLC | Georgetown | 50 | 1 | 2026 | Under construction |
| Bush River Solar PlantSolar Photovoltaic | Duke Energy Carolinas, LLC | Laurens | 45 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| Cotton SolarSolar Photovoltaic | Cotton Solar, LLC | Dillon | 16 | 1 | 2027 | Regulatory approvals received. Not under construction |
| Rhubarb One SCSolar Photovoltaic | SolRiver Capital LLC | Marion | 9.6 | 1 | 2027 | Regulatory approvals pending. Not under construction |
Where they are in the build
- Regulatory approvals received. Not under construction16
- Regulatory approvals pending. Not under construction4
- Under construction2
- Construction complete1
Planned solar farms in South Carolina: FAQ
- How many solar farms are planned in South Carolina?
- 23, for 2 GW of nameplate capacity. These are generators developers have reported as planned, not generators that exist.
- What do the status letters mean?
- Each planned generator carries a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. Projects are canceled or postponed, and move in and out of the planned list month to month. This page lists what was planned as of 2026-07 and nothing more.