Planned wind farms in Texas
What EIA-860M's Planned sheet says is coming in Texas: 22 wind farms totalling 5 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Planned projects
- 22
- 22 generating units
- Proposed capacity
- 5 GW
- Earliest in-service year
- 2026
- Latest in-service year
- 2030
Map of planned wind farms in Texas
Loading map…
List of planned wind farms in Texas
| IP Roman WindOnshore Wind Turbine | Intersect USA, LLC | Deaf Smith | 670.5 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| IP Meitner WindOnshore Wind Turbine | Intersect USA, LLC | Roberts | 500 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| Hubbard Wind IIOnshore Wind Turbine | Hubbard Wind II, LLC | Hill | 304.5 | 1 | 2026 | Under construction |
| Changing WindsOnshore Wind Turbine | Invenergy Services LLC | Castro | 288 | 1 | 2028 | Regulatory approvals pending. Not under construction |
| Monarch Creek Wind, LLCOnshore Wind Turbine | Monarch Creek Wind, LLC | Throckmorton | 287.6 | 1 | 2027 | Under construction |
| Blue Hills Wind ProjectOnshore Wind Turbine | Greenalia Wind Power Blue Hills, LLC | Val Verde | 276 | 1 | 2029 | Regulatory approvals pending. Not under construction |
| Yellow Cat Wind, LLCOnshore Wind Turbine | RWE Clean Energy | Navarro | 270 | 1 | 2026 | Under construction |
| Goodnight Wind IIOnshore Wind Turbine | FGE Goodnight II, LLC | Armstrong | 265.5 | 1 | 2027 | Under construction |
| Big Sampson WindOnshore Wind Turbine | Big Sampson Wind Project, LLC | Crockett | 265 | 1 | 2026 | Construction complete |
| Lazbuddie Wind Energy LLCOnshore Wind Turbine | Invenergy Services LLC | Parmer | 265 | 1 | 2026 | Under construction |
| Throckmorton WindOnshore Wind Turbine | Throckmorton Wind, LLC | Haskell | 225.6 | 1 | 2026 | Under construction |
| Willow Beach WindOnshore Wind Turbine | AES Clean Energy | Brazoria | 200 | 1 | 2029 | Regulatory approvals pending. Not under construction |
| Honey Mesquite Wind, LLCOnshore Wind Turbine | RWE Clean Energy | Sterling | 180.5 | 1 | 2026 | Under construction |
| Water Valley Wind EnergyOnshore Wind Turbine | Tri Global Energy, LLC | Tom Green | 180 | 1 | 2027 | Planned for installation |
| Bob Creek Wind, LLCOnshore Wind Turbine | Bob Creek Wind, LLC | Sterling | 175 | 1 | 2028 | Planned for installation |
| Bluebonnet Prairie WindOnshore Wind Turbine | Leeward Asset Management, LLC | Navarro | 170 | 1 | 2027 | Under construction |
| Carol Wind, LLCOnshore Wind Turbine | Carol Wind, LLC | Potter | 167.8 | 1 | 2027 | Regulatory approvals received. Not under construction |
| McCrae Wind Energy IIOnshore Wind Turbine | McCrae Wind Energy II, LLC | Glasscock | 162.1 | 1 | 2026 | Construction complete |
| EasterOnshore Wind Turbine | Enbridge Wind (Easter), LLC | Castro | 152 | 1 | 2027 | Under construction |
| Cone Renewable Energy Project, LLCOnshore Wind Turbine | Cone Renewable Energy Project, LLC | Crosby | 150 | 1 | 2027 | Regulatory approvals pending. Not under construction |
| Pioneer Field Wind PowerOnshore Wind Turbine | Greenalia Wind Power Pioneer Field, LLC | Tom Green | 136.2 | 1 | 2030 | Planned for installation |
| Blackwelder Ranch WindOnshore Wind Turbine | Greenalia Wind Power Blackwelder Ranch, LLC | Pecos | 110.4 | 1 | 2030 | Planned for installation |
Where they are in the build
- Regulatory approvals pending. Not under construction6
- Under construction6
- Planned for installation4
- Under construction3
- Construction complete2
- Regulatory approvals received. Not under construction1
Planned wind farms in Texas: FAQ
- How many wind farms are planned in Texas?
- 22, for 5 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
- What do the status letters mean?
- EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
- Do these projects always get built?
- No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.