BWC Origination 8 LLC Sturbridge 2

BWC Origination 8 LLC Sturbridge 2 is a 1 MW solar farm in Worcester County, Massachusetts, operated by BWC Origination 8 LLC Sturbridge 2 LLC. EIA-860M lists 1 generating unit here, inside ISO New England. Its unit entered service in 2017.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Nameplate capacity
1 MW
1 MW net summer
Generating units
1
In service
2017
EIA plant ID
69127

Where it is

Loading map…
County
Worcester County, Massachusetts
Coordinates
42.1189, -72.0697
Balancing authority
ISNE
Sector
IPP Non-CHP

Units, technology and status

Operator of record
BWC Origination 8 LLC Sturbridge 2 LLC
Primary energy source
Solar
Technologies
Solar Photovoltaic
Status
Operating

Every plant BWC Origination 8 LLC Sturbridge 2 LLC reports to EIA →

BWC Origination 8 LLC Sturbridge 2: FAQ

Where is BWC Origination 8 LLC Sturbridge 2?
In Worcester County, Massachusetts (MA). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
How big is BWC Origination 8 LLC Sturbridge 2?
1 MW of nameplate capacity across 1 unit, as of the EIA-860M release for 2026-07.
Who owns BWC Origination 8 LLC Sturbridge 2?
EIA-860M names BWC Origination 8 LLC Sturbridge 2 LLC as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
Is this the same as BWC Origination 8 LLC Sturbridge 2 LLC?
Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — BWC Origination 8 LLC Sturbridge 2 LLC here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "BWC Origination 8 LLC Sturbridge 2 LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
Is BWC Origination 8 LLC Sturbridge 2 still running?
EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.