MCRD Parris Island PV Hybrid

MCRD Parris Island PV Hybrid is a 17 MW solar farm in Beaufort County, South Carolina, operated by Ameresco Federal Solutions. EIA-860M lists 7 generating units here. Its units entered service between 2018 and 2019.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Nameplate capacity
17 MW
17 MW net summer
Generating units
7
In service
2018–2019
EIA plant ID
61956

Where it is

Loading map…
County
Beaufort County, South Carolina
Coordinates
32.3294, -80.6947
Balancing authority
SCEG
Sector
IPP Non-CHP

Units, technology and status

Operator of record
Ameresco Federal Solutions
Primary energy source
Solar
Technologies
Batteries, Natural Gas Fired Combustion Turbine, Petroleum Liquids, Solar Photovoltaic
Status
Operating

This site runs on more than one energy source. EIA-860M capacity splits: Solar 6 MW, Battery 4 MW, Natural gas 4 MW, Petroleum 4 MW. It is filed here under Solar, the source with the most capacity.

Every plant Ameresco Federal Solutions reports to EIA →

MCRD Parris Island PV Hybrid: FAQ

Where is MCRD Parris Island PV Hybrid?
In Beaufort County, South Carolina (SC). The map on this page is placed at the coordinates EIA files for the plant, which locate the site rather than any individual unit.
How big is MCRD Parris Island PV Hybrid?
17 MW of nameplate capacity across 7 units, as of the EIA-860M release for 2026-07.
Who owns MCRD Parris Island PV Hybrid?
EIA-860M names Ameresco Federal Solutions as the reporting entity. That is the operator of record on the survey, which is not always the ultimate owner.
Is this the same as MCRD Parris Island PV Hybrid LLC?
Probably, but EIA-860M does not say. The survey records a plant name and a reporting entity — Ameresco Federal Solutions here — not the project company that holds the asset. Project companies are commonly registered as an LLC carrying the plant's name, so a search for "MCRD Parris Island PV Hybrid LLC" usually means this site. This page shows only what EIA files, and does not assert a corporate structure it cannot see.
Is MCRD Parris Island PV Hybrid still running?
EIA-860M files it as "Operating" for 2026-07. Statuses change monthly, and this page follows the monthly release.