Planned wind farms in New York

What EIA-860M's Planned sheet says is coming in New York: 9 wind farms totalling 3 GW, each with the in-service year its developer reported and the construction status EIA records. A planned project is not a built one.

As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m

Planned projects
9
11 generating units
Proposed capacity
3 GW
Earliest in-service year
2026
Latest in-service year
2029

Map of planned wind farms in New York

Loading map…

List of planned wind farms in New York

Planned wind farms in New York
Sunrise WindOffshore Wind TurbineOrsted Wind Power North America LLCSuffolk92412027Under construction
Empire Wind 1Offshore Wind TurbineEmpire Offshore Wind LLCKings81012027Under construction
Alle-Catt Wind Energy LLCOnshore Wind TurbineInvenergy Services LLCAllegany34012026Under construction
Heritage WindOnshore Wind TurbineHeritage Wind, LLCOrleans12612028Planned for installation
Hoffman Falls Wind 2Onshore Wind TurbineLiberty Renewables IncorporatedMadison103.512029Planned for installation
High Bridge Wind ProjectOnshore Wind TurbineHigh Bridge Wind, LLCChenango103.212027Planned for installation
Agricola WindOnshore Wind TurbineLiberty Renewables IncorporatedCayuga9912029Planned for installation
Rolling Upland Wind Farm LLCOnshore Wind TurbineRolling Upland Wind Farm LLCMadison71.412029Planned for installation
Cody Road Wind FarmOnshore Wind TurbineGreen Power Energy LLCMadison7.232029Under construction

Where they are in the build

  • Planned for installation5
  • Under construction2
  • Under construction2

Planned wind farms in New York: FAQ

How many wind farms are planned in New York?
9, for 3 GW of nameplate capacity. These are generators developers have reported to EIA, not generators that exist.
What do the status letters mean?
EIA files each planned generator under a status: regulatory approvals pending, under construction at or below half complete, under construction more than half complete, construction complete but not yet in commercial operation, or planned but not yet started. Each row shows its own.
Do these projects always get built?
No. EIA keeps a separate Canceled or Postponed sheet, and projects move between the sheets month to month. This page is the Planned sheet for 2026-07 and nothing more.