SolRiver Capital power plants
Every generating plant EIA-860M files against SolRiver Capital for 2026-07: 25 plants, 110 MW of nameplate capacity, across 7 states and 1 energy source.
EIA files this entity as “SolRiver Capital LLC”.
As of 2026-07 (inventory dated 2026-07-31) · EIA-860M Preliminary Monthly Electric Generator Inventory · eia.gov/…/july_generator2026.xlsx · eia.gov/…/eia860m
- Plants
- 25
- Nameplate capacity
- 110 MW
- States
- 7
- GA, IN, NC, NY, OR, PA, SC
- Energy sources
- 1
SolRiver Capital plants by energy source
- Solar25 plants · 110 MW
Full list of SolRiver Capital power plants
| Whitetail SolarSolar Photovoltaic | SolRiver Capital LLC | Dillon | 10 | 1 | 2021 | Operating |
| Sunflower Solar LLCSolar Photovoltaic | SolRiver Capital LLC | Williamsburg | 10 | 1 | 2024 | Operating |
| Shorthorn HoldingsSolar Photovoltaic | SolRiver Capital LLC | Marlboro | 8.9 | 1 | 2023 | Operating |
| C&B Graham Energy, LLCSolar Photovoltaic | SolRiver Capital LLC | Hendricks | 7 | 1 | 2023 | Operating |
| Washington SolarSolar Photovoltaic | SolRiver Capital LLC | Rockingham | 5 | 1 | 2024 | Operating |
| Elk Solar LLCSolar Photovoltaic | SolRiver Capital LLC | Hoke | 5 | 1 | 2024 | Operating |
| Longleaf Pine Solar LLCSolar Photovoltaic | SolRiver Capital LLC | Davie | 5 | 1 | 2025 | Operating |
| Williams Solar LLCSolar Photovoltaic | SolRiver Capital LLC | Johnston | 5 | 1 | 2025 | Operating |
| Gray Fox Solar LLCSolar Photovoltaic | SolRiver Capital LLC | Robeson | 5 | 1 | 2024 | Operating |
| McLean HomesteadSolar Photovoltaic | SolRiver Capital LLC | Scotland | 4.9 | 1 | 2023 | Operating |
| Warbler HoldingsSolar Photovoltaic | SolRiver Capital LLC | Cleveland | 4 | 1 | 2021 | Operating |
| Butler Solar, LLCSolar Photovoltaic | SolRiver Capital LLC | Yamhill | 4 | 1 | 2021 | Operating |
| Hunker Solar River, LLCSolar Photovoltaic | SolRiver Capital LLC | Westmoreland | 3.3 | 1 | 2021 | Operating |
| Bulloch County GA S4 LLCSolar Photovoltaic | SolRiver Capital LLC | Bulloch | 3 | 1 | 2023 | Operating |
| Bulloch County GA S3 LLCSolar Photovoltaic | SolRiver Capital LLC | Bulloch | 3 | 1 | 2023 | Operating |
| Richmond County GA S2 LLCSolar Photovoltaic | SolRiver Capital LLC | Richmond | 3 | 1 | 2023 | Operating |
| Upson County GA S1 LLCSolar Photovoltaic | SolRiver Capital LLC | Upson | 3 | 1 | 2023 | Operating |
| Harding Solar, LLCSolar Photovoltaic | SolRiver Capital LLC | Greene | 3 | 1 | 2024 | Operating |
| Sheridan Solar LLC (CSG)Solar Photovoltaic | SolRiver Capital LLC | Yamhill | 3 | 1 | 2024 | Operating |
| Wallace Solar LLC (CSG)Solar Photovoltaic | SolRiver Capital LLC | Polk | 3 | 1 | 2024 | Operating |
| Green Solar LLC (CSG)Solar Photovoltaic | SolRiver Capital LLC | Jefferson | 2.9 | 1 | 2024 | Operating |
| Marble Solar LLC (CSG)Solar Photovoltaic | SolRiver Capital LLC | Linn | 2.9 | 1 | 2024 | Operating |
| Auburn Solar LLC (CSG)Solar Photovoltaic | SolRiver Capital LLC | Clackamas | 2.9 | 1 | 2024 | Operating |
| Whitehall Solar LLCSolar Photovoltaic | SolRiver Capital LLC | Florence | 2 | 1 | 2024 | Operating |
| RIT Henrietta Solar 1, LLCSolar Photovoltaic | SolRiver Capital LLC | Monroe | 1.6 | 1 | 2018 | Operating |
SolRiver Capital: FAQ
- How many power plants does SolRiver Capital operate?
- EIA-860M lists 25 operating plants against “SolRiver Capital LLC” for 2026-07, totalling 110 MW of nameplate capacity in 7 states.
- Is SolRiver Capital the owner of these plants?
- EIA-860M names one reporting entity per generator. That entity operates the plant on the survey; ownership can sit with a parent, a partnership or a tax-equity structure that the form does not record.
- Why are affiliates listed separately?
- Because EIA files them separately. Rolling subsidiaries into a parent would need an ownership map EIA-860M does not publish, so this page does not invent one.